We moved to Buxton in August last year after spending most of the year trying to find a suitable house. As seems to be normal these days, with moving house, we had plenty of stress and anxiety - enough for the next few years put together! The buyers of our house in Swindon threatened to pull out, the sellers of the house in Buxton were getting all agressive about us doing surveys (now we know why!) and the bank only just gave us a mortgage the day before the move.
Anyway we moved in (and by-the-way the removal company were fab so I'll give Advance Removals a mention) and since then we've changed the kitchen, put in new windows, loft insulation, new boiler, had the electrics updated, a new gas meter and put in a downstairs toilet, all in time for our new arrival, Adam, who was born on the 14th December last year. Phew! Quite a year! Hence this is the first blog post for a while.
The other project was to create a place for me to work, for this we plan to convert the garage into an enamelling workshop/studio. Well this is the progress to date:
2nd Nov 2014

Our garage is the left-hand one, it has rot in the beams and damp problems galore!
So to work! We employed the skills of brothers Shaun and Gavin Hall, who, as a piece of sound advice, call themselves 'Don't Do It Yourself'. Advice from which the previous owners of our house would benefit!
6th Nov 2014

The walls have all been pressure-washed to remove the old paint and plaster. The wall insulation is going in on the neighbour-side of the workshop.
7th Nov 2014

The walls at the back and on the left have been covered with GRS slurry waterproofing since these back onto a hill and are, effectively, underground. The right-hand side wall has been finished with water-resistant chipboard.
10th Nov 2014

The insulation goes in on the left-hand-side wall too, we're using 50mm Kingspan for the walls.
11th Nov 2014

Walls finished with water-resistant chipboard and a new mezzanine floor is put in - the old one was too rotten to salvage. Mind you we got quite a lot of fire-wood from it!
12 Dec 2014 (or thereabouts, the 12th is when I took the photo!)

The new ceiling goes in with the Velux windows. We've used 100mm of Kingspan for the roof, done in 75mm and 25mm separated layers. The 75mm sections lie in-between the wooden rafters and the 25mm sections overlap to cut out the thermal bridge. The original waterproof sheet has been replaced with a semi-permeable membrane. The outside wall needs cementing and the roof-wall interface sorting out as there's still water coming in at the back! We've put in plenty of electrical sockets too, I hate moving things around and extension cables can be a liability in a workshop.
13 Dec 2014 - 2 Feb 2015
Wind, rain and lots of snow! Any work has had to halt. In the meantime here are some nice pictures of snowy Buxton: